How long GujRERA takes to approve a Dholera project: days from application to approval, project by project

Updated 17 November 2026. Compiled by the DholeraHelp desk from the sources listed at the end of this page.

On the GujRERA register read on 17 November 2026, the days between a Dholera project's registration application and the approval date shown range from 22 to 153, with a median of 49 across the 33 registered projects. The shortest counts are ABCD Enclave IV by Smarthomes Infrastructre Private Limited at 22 days, then Platinum 8, Dholera Marigold 548 and Piccadilly Square II at 28 days each.

  • 22 daysshortest count on the register
  • 153 dayslongest count on the register
  • 49 daysmedian of the 33 projects
  • 17 Nov 2026date the register was read
Check any developer here firstLook the company up on DholeraIntel's developer directory and read how to verify a Dholera developer before you pay. Then confirm the project's registration on the GujRERA portal and ask for the title papers of the exact plot. A place on this list records a public fact about a company. It is a starting point for your own checks.DholeraIntel is a sister publication of this site.
How this list is rankedRanked on one fact: the number of days between the application date and the approval date shown on the register, taken from the Registration application row of each project's list of applications on the GujRERA public register, read on 17 November 2026. Days are the approval date minus the application date. All 33 registered Dholera projects carry both dates, so none is left out; equal counts share a rank and the shortest count comes first. The count includes any time the file waited on the promoter for papers, which the register does not separate.

Registered projects by days between application and approval

RankPromoter (as on the record)ProjectGujRERA numberApplication submittedApproval date shownDays between application and approvalProject type
1Smarthomes Infrastructre Private LimitedABCD Enclave IVPR/GJ/AHMEDABAD/DHANDHUKA/DSIRDA/PN70AA09970/08062217 May 20228 June 202222Plotted Development
2=7 Oak DevelopersPlatinum 8PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08209/17032117 February 202117 March 202128Plotted Development
2=CT Corporation (proprietorship)Dholera Marigold 548PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07648/09112012 October 20209 November 202028Plotted Development
2=Smart Dholera Housing Private LimitedPiccadilly Square IIPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PN36AA09936/21052223 April 202221 May 202228Plotted Development
5Pacificus Superinfra LLPPalm Greens Platinum 2PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09395/EX1/240326/3112262 November 20211 December 202129Plotted Development
6Seksaria Buildcon LLPShantiban SkylarPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/31122915 November 202515 December 202530Mixed Development
7Cube InfrastructureNest 63PR/GJ/AHMEDABAD/AHMEDABAD CITY/Others/PAA10662/15092212 August 202215 September 202234Plotted Development
8Greenera Infrawell Private LimitedGreenera Prime 1PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07785/16122010 November 202016 December 202036Plotted Development
97 Oak DevelopersPlatinum 7PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08002/03022128 December 20203 February 202137Plotted Development
10Chhabildas Developers Private LimitedDholera SkyPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07924/1601219 December 202016 January 202138Plotted Development
11Fidato BuildconFidato Luxuria 2PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09239/27102117 September 202127 October 202140Plotted Development
127 Oak Developers7 Oak Smart CityPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07929/1801218 December 202018 January 202141Plotted Development
13Greenera Infrawell Private LimitedGreenera GardenvillaPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/30122523 July 20205 September 202044Plotted Development
14Aaiji Infra and DevelopersAaiji ResidencyPR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA09145/11102126 August 202111 October 202146Plotted Development
15Infinity Infracon (proprietorship)Park ViewPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10465/1807221 June 202218 July 202247Plotted Development
16Shyam InfraDholera IconicPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/CAA16655/010426/31033012 February 20261 April 202648Commercial
17=7 Oak Developers Private LimitedPlatinum 9PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10275/06062218 April 20226 June 202249Plotted Development
17=GAP Associates Private LimitedGAP Industrial Park 1PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10173/EX1/030826/31122623 March 202211 May 202249Plotted Development
19Greenera Infrawell Private LimitedGreenera Prime 2PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07841/31122011 November 202031 December 202050Plotted Development
20Fidato BuildconFidato Luxuria 3PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08562/04062114 April 20214 June 202151Plotted Development
21=7 Oak Developers7 Oak Platinum 4PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07741/05122013 October 20205 December 202053Plotted Development
21=GAP Studios LLPAakarPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/RAA15713/190825/31122827 June 202519 August 202553Residential/Group Housing
23=Fidato BuildconFidato LuxuriaPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07658/10112017 September 202010 November 202054Plotted Development
23=Parv Infracon LLPShantiban DreamsPR/GJ/AHMEDABAD/AHMEDABAD CITY/Dholera Special Investment Region Development Authority/MAA11736/A1M/281026/31122815 March 20238 May 202354Mixed Development
25Greenera Infrawell Private LimitedGreenera Gardenvilla 2PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA11450/EX1/010925/30052618 January 202314 March 202355Plotted Development
26Cube InfraNest 29PR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA07781/16122020 October 202016 December 202057Plotted Development
27Satyaja InfratechBliss 107PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12751/040124/3103286 November 20234 January 202459Plotted Development
28Dholera Mega City 771Dholera Megacity 771PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10217/2005228 March 202220 May 202273Plotted Development
29Satyaja InfratechPrelude Industrial ParkPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12807/240124/3103286 November 202324 January 202479Plotted Development
30Infinity Infracon (proprietorship)Dholera Megacity IrisPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10133/0205228 February 20222 May 202283Plotted Development
31Aaiji Infraspace(OPC) Private LimitedAaiji Residency 477PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA15497/110725/3112294 April 202511 July 202598Plotted Development
32Satyaja InfraconBliss Grandeur- 2PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12719/211223/3103284 August 202321 December 2023139Plotted Development
33Satyaja InfraconBliss Grandeur- 1PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12734/030124/3103283 August 20233 January 2024153Plotted Development

All 33 registered projects carry both dates on the Registration application row of the register and are ranked, fewest days first; equal counts share a rank (marked =). Days between = approval date minus application submission date, as printed on the register, read 17 November 2026. Median 49 days, range 22 to 153 days. The count includes any time the file waited on the promoter, which the register does not separate.

Download this table (CSV). Last checked 17 November 2026. Free to quote with a link to this page.

Days between the registration application date and the approval date shown, GujRERA register read 17 November 2026
ABCD Enclave IV22
Platinum 828
Dholera Marigold 54828
Piccadilly Square II28
Palm Greens Platinum 229
Shantiban Skylar30
Nest 6334
Greenera Prime 136
Platinum 737
Dholera Sky38
Fidato Luxuria 240
7 Oak Smart City41
Greenera Gardenvilla44
Aaiji Residency46
Park View47
Dholera Iconic48
Platinum 949
GAP Industrial Park 149
Greenera Prime 250
Fidato Luxuria 351
7 Oak Platinum 453
Aakar53
Fidato Luxuria54
Shantiban Dreams54
Greenera Gardenvilla 255
Nest 2957
Bliss 10759
Dholera Megacity 77173
Prelude Industrial Park79
Dholera Megacity Iris83
Aaiji Residency 47798
Bliss Grandeur- 2139
Bliss Grandeur- 1153

Bars show all 33 registered projects, fewest days first.

1. ABCD Enclave IV, Smarthomes Infrastructre Private Limited

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/DSIRDA/PN70AA09970/080622
  • Application submitted17 May 2022
  • Approval date shown8 June 2022
  • Days between22
  • Project typePlotted Development

The register shows the registration application submitted on 17 May 2022 and approved on 8 June 2022, 22 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

2. Platinum 8, 7 Oak Developers

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08209/170321
  • Application submitted17 February 2021
  • Approval date shown17 March 2021
  • Days between28
  • Project typePlotted Development

The register shows the registration application submitted on 17 February 2021 and approved on 17 March 2021, 28 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

3. Dholera Marigold 548, CT Corporation (proprietorship)

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07648/091120
  • Application submitted12 October 2020
  • Approval date shown9 November 2020
  • Days between28
  • Project typePlotted Development

The register shows the registration application submitted on 12 October 2020 and approved on 9 November 2020, 28 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

4. Piccadilly Square II, Smart Dholera Housing Private Limited

  • GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PN36AA09936/210522
  • Application submitted23 April 2022
  • Approval date shown21 May 2022
  • Days between28
  • Project typePlotted Development

The register shows the registration application submitted on 23 April 2022 and approved on 21 May 2022, 28 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

5. Palm Greens Platinum 2, Pacificus Superinfra LLP

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09395/EX1/240326/311226
  • Application submitted2 November 2021
  • Approval date shown1 December 2021
  • Days between29
  • Project typePlotted Development

The register shows the registration application submitted on 2 November 2021 and approved on 1 December 2021, 29 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

6. Shantiban Skylar, Seksaria Buildcon LLP

  • GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/311229
  • Application submitted15 November 2025
  • Approval date shown15 December 2025
  • Days between30
  • Project typeMixed Development

The register shows the registration application submitted on 15 November 2025 and approved on 15 December 2025, 30 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

7. Nest 63, Cube Infrastructure

  • GujRERA numberPR/GJ/AHMEDABAD/AHMEDABAD CITY/Others/PAA10662/150922
  • Application submitted12 August 2022
  • Approval date shown15 September 2022
  • Days between34
  • Project typePlotted Development

The register shows the registration application submitted on 12 August 2022 and approved on 15 September 2022, 34 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

8. Greenera Prime 1, Greenera Infrawell Private Limited

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07785/161220
  • Application submitted10 November 2020
  • Approval date shown16 December 2020
  • Days between36
  • Project typePlotted Development

The register shows the registration application submitted on 10 November 2020 and approved on 16 December 2020, 36 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

9. Platinum 7, 7 Oak Developers

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08002/030221
  • Application submitted28 December 2020
  • Approval date shown3 February 2021
  • Days between37
  • Project typePlotted Development

The register shows the registration application submitted on 28 December 2020 and approved on 3 February 2021, 37 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

10. Dholera Sky, Chhabildas Developers Private Limited

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07924/160121
  • Application submitted9 December 2020
  • Approval date shown16 January 2021
  • Days between38
  • Project typePlotted Development

The register shows the registration application submitted on 9 December 2020 and approved on 16 January 2021, 38 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

11. Fidato Luxuria 2, Fidato Buildcon

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09239/271021
  • Application submitted17 September 2021
  • Approval date shown27 October 2021
  • Days between40
  • Project typePlotted Development

The register shows the registration application submitted on 17 September 2021 and approved on 27 October 2021, 40 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

12. 7 Oak Smart City, 7 Oak Developers

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07929/180121
  • Application submitted8 December 2020
  • Approval date shown18 January 2021
  • Days between41
  • Project typePlotted Development

The register shows the registration application submitted on 8 December 2020 and approved on 18 January 2021, 41 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

13. Greenera Gardenvilla, Greenera Infrawell Private Limited

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225
  • Application submitted23 July 2020
  • Approval date shown5 September 2020
  • Days between44
  • Project typePlotted Development

The register shows the registration application submitted on 23 July 2020 and approved on 5 September 2020, 44 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

14. Aaiji Residency, Aaiji Infra and Developers

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA09145/111021
  • Application submitted26 August 2021
  • Approval date shown11 October 2021
  • Days between46
  • Project typePlotted Development

The register shows the registration application submitted on 26 August 2021 and approved on 11 October 2021, 46 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

15. Park View, Infinity Infracon (proprietorship)

  • GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10465/180722
  • Application submitted1 June 2022
  • Approval date shown18 July 2022
  • Days between47
  • Project typePlotted Development

The register shows the registration application submitted on 1 June 2022 and approved on 18 July 2022, 47 days apart. That is below the median of 49 days for the 33 projects.

The count includes any days the file waited for the promoter to supply papers or answer a query, which the register does not separate from the authority's own handling time.

Who this page is for

This page is for a buyer or a reader who has asked how long the regulator takes to register a Dholera project, and for a promoter's customer who wants to read the dates on a project's record correctly. It gives the counts as the register prints them, project by project, so you can see the spread and not only an average. The days run from application to approval for each builder or developer, and the register gives no reason for a short or long count.

Which dates these are

Each project's record on the GujRERA register lists its applications. The first is the Registration application, which carries a date it was submitted and a date it was approved. This page subtracts one from the other. For all 33 projects the approval date is the same as the registration date printed on the project's record.

Other application types on the record, such as extensions, annual compliance and complaints, are not part of this count.

How the 33 counts spread

Six projects show 30 days or fewer, 21 show 31 to 60 days, four show 61 to 100 days and two show more than 100: Bliss Grandeur 2 at 139 days and Bliss Grandeur 1 at 153 days. The median is 49 days and the range is 22 to 153 days.

By the year the application was submitted, the medians are 42.5 days for 10 applications in 2020, 40 days for 5 in 2021, 48 days for 8 in 2022, 69 days for 6 in 2023, 53 days for 3 in 2025 and 48 days for the single application in 2026. Each group is small, so the differences between years are not a trend.

What the Act says about time

Section 5 of the Real Estate (Regulation and Development) Act 2016 says the Authority shall, within thirty days of receiving the application, grant registration or reject the application in writing. This page does not test any project against that period. The register does not show the day an application was complete, whether the Authority asked the promoter for more papers, or how long the promoter took to reply, so a count above or below 30 days cannot be read as a statement about the regulator or the promoter.

What the count does not tell you

The count says nothing about the quality of a project, its title, its price or when a plot will be handed over. It covers one step, the registration, on the days the register shows. It also includes weekends and holidays, because it is a plain difference between two dates.

Two projects in the table were registered under the same promoter name on consecutive days of application, and others share a promoter across years, so the figures belong to applications and not to companies.

How to check a project's dates yourself in five minutes

  1. Open gujrera.gujarat.gov.in and search the project by the name or GujRERA number printed in the table.
  2. Open the project's page and find its list of applications.
  3. Look at the row for the Registration application and note the submitted date and the approved date.
  4. Count the days between them, or use the date difference tool in a spreadsheet.
  5. Compare the approved date with the registration date printed on the project's record. They should match, as they do for all 33 projects here.

What changed since August

No registration date changed between the 4 August and 17 November reads, and the same 33 projects were on the register on both dates. The 57 fields that did change were declared completion dates, quarterly filings, complaint statuses and one project area, none of which is used here. The application dates in this table were first read on 17 November 2026.

What this list cannot tell you

The count includes any time the file waited on the promoter for papers, which the register does not separate, and it says nothing about the quality of a project. It covers the registration step only, for the 33 Dholera projects on the GujRERA register on 17 November 2026. It cannot tell you whether a layout is legally clear, what a plot costs or when it will be delivered.

Questions people ask

How long does GujRERA take to approve a project registration in Dholera?

For the 33 Dholera projects on the register read on 17 November 2026, the days between application and the approval date shown range from 22 to 153, with a median of 49. Each project's own dates are in the table. The count includes any time the file waited on the promoter.

What time limit does the RERA Act set for approving a project registration?

Section 5 of the Real Estate (Regulation and Development) Act 2016 says the Authority shall, within thirty days of receiving the application, grant the registration or reject the application in writing. The register does not show when an application was complete, so this page does not test projects against it.

Which Dholera project had the fewest days between application and approval?

ABCD Enclave IV by Smarthomes Infrastructre Private Limited, at 22 days between the application date of 17 May 2022 and the approval date of 8 June 2022. Three projects share the next count of 28 days: Platinum 8, Dholera Marigold 548 and Piccadilly Square II.

Does a shorter approval time mean a better Dholera project?

No. The count measures one step on the record and includes any time the file waited on the promoter. It says nothing about the quality, title, price or delivery of a project. Read the project's registration, approvals and progress reports instead.

Where can I see the application and approval dates of a Dholera project?

On the GujRERA public register, open the project's page and find its list of applications. The Registration row shows the submitted date and the approved date. The table on this page prints both dates and the difference for all 33 registered Dholera projects.

Why do some Dholera registrations show more than 100 days?

The register does not give a reason. Two of the 33 show more than 100 days, Bliss Grandeur 2 at 139 and Bliss Grandeur 1 at 153. The count includes any time the file waited for papers or replies, so the days cannot be assigned to one side.

Read next

Sources

  1. GujRERA public register, Dholera project records (read 17 November 2026)
  2. GujRERA project applications endpoint, example record 10840 (7 Oak Platinum 4) (read 17 November 2026)
  3. Real Estate (Regulation and Development) Act 2016, section 5, grant of registration (text of the Act as reproduced on courtbook.in) (read 17 November 2026)
  4. GujRERA public register, Dholera records for the August comparison (read 4 August 2026)